Pavement Work Base Layer Driveway Aprons

On Wednesday, September 21, 2022, the Town of Millbury’s Department of Public Works / Highway Department’s subcontractor, J.H. Lynch & Sons, Inc., has started laying down the base (binder) layer of asphalt on the driveway aprons and sidewalks serving households on Thomas Hill Road, Aldrich Avenue, and Captain Peter Simpson Road and will start hydroseeding… Continue reading Pavement Work Base Layer Driveway Aprons

Pavement Work Finish Layer Update

On Friday, September 2, 2022, the Town of Millbury’s Department of Public Works / Highway Department’s subcontractor, J.H. Lynch & Sons, Inc., laying down the final layer of asphalt on Thomas Hill Road, Aldrich Avenue, and Captain Peter Simpson Road. It is assumed, but not confirmed, that Rice Road will follow next week between the… Continue reading Pavement Work Finish Layer Update

Pavement Work Finish Layer

On Friday, September 2, 2022, the Town of Millbury’s Department of Public Works / Highway Department’s subcontractor, J.H. Lynch & Sons, Inc., has begun laying down the final layer of asphalt throughout our neighborhood of Rice Road, Thomas Hill Road, Aldrich Avenue, and Captain Peter Simpson Road. Therefore, no one should be stopped or parked… Continue reading Pavement Work Finish Layer

Pavement Work Raising Structures

On Wednesday, August 24, 2022, the Town of Millbury’s Department of Public Works / Highway Department’s subcontractor, J.H. Lynch & Sons, Inc., began raising structures throughout our neighborhood of Rice Road, Thomas Hill Road, Aldrich Avenue, and Captain Peter Simpson Road. The Millbury Department of Public Works / Highway Department are still waiting for the… Continue reading Pavement Work Raising Structures

Pavement Work Base Layer Complete

On Monday, August 15, 2022, the Town of Millbury’s Department of Public Works / Highway Department’s subcontractor, J.H. Lynch & Sons, Inc., completed laying down the base layer of asphalt onto the gravel base throughout our neighborhood of Rice Road, Thomas Hill Road, Aldrich Avenue, and Captain Peter Simpson Road, and partially reconfigured the T… Continue reading Pavement Work Base Layer Complete

Pavement Work Base Layer

On Tuesday, August 9, 2022, the Town of Millbury’s Department of Public Works / Highway Department’s subcontractor, J.H. Lynch & Sons, Inc., has begun laying down the base layer of asphalt onto the gravel base. They began on the lower part of Captain Peter Simpson Road and will be working their way through our neighborhood… Continue reading Pavement Work Base Layer

Pavement Work To Begin

The Millbury Department of Public Works’ subcontractor will commence the work necessary to resurface Rice Road, Thomas Hill Road, Aldrich Avenue, and Captain Peter Simpson Road between Tuesday, August 2, 2022 (tomorrow) through Friday, August 12, 2022, subject to weather conditions and other variables in their schedules. The pavement subcontractor will begin with removing and… Continue reading Pavement Work To Begin